Agency Name: CAM Construction & Properties
DCS Project Number: 08427
DCS Project Name: WCC/Cottonwood Creek Phase II/
DCS Project Description: Cottonwood Creek Phase II/Renovation of Existing Pump Pad and Water Delivery System on the Cottonwood Creek Wetland Development Units/Creek County, OK.
Project Manager Name: GEORGE VERSTRAETE
Project Manager Email: George.Verstraete@omes.ok.gov

Project Manager Phone Number: (405)522-1639
Bid Closing Date:
Bid Status: N/A
Pre-Bid Meeting Date:
Pre-Bid Meeting Time: N/A
Is the Pre-Bid Meeting Mandatory? Yes
Pre-Bid Meeting Details: N/A

N/A
Addenda: 0

N/A
Contract Award Letter Sent To Agency: 05/06/2009
Contract Award Letter Received from the Agency: N/A
Contract Sent To Vendor For Signature: N/A
Contract Received from Vendor: N/A
Contract Sent To Agency For Signature: N/A
Contract Received from Agency: N/A
Awarded Vendor: Blazer Oilfield Services, LLC
Awarded Amount: $422,665.00
Notice To Proceed: N/A
Disclaimer Message:
Notes:
  • It is the Bidder's responsibility to check the DCS/Construction & Properties website frequently for any possible addendas that may be issued.
  • In order to receive payments from the State of Oklahoma, suppliers who are not registered on the State of Oklahoma Vendor Registration list must complete the "Vendor/Payee Form" (www.ok.gov/OSF/documents/osfvend.pdf). Non-U.S. suppliers who are not registered on the State of Oklahoma Vendor Registration List must complete a W-8BEN (www.irs.gov/pub/irs-pdf/fw8ben.pdf). Failure to do so may delay contract award.
  • If documents listed on this page do not meet your accessibility requirements, please contact DCS at (405) 521-2112 and appropriate accommodations will be made.
  • If you are looking for a Project Manager's contact information, please click CAP Contact List.
  • We recommend you use the latest version of Adobe Reader. If you need to download Adobe Reader, here is a link to the Adobe WebSite (http://get.adobe.com/reader/).